Cost
effectiveness
|
| Necessary
time for blinding or deblinding |
|
|
|
|
|
Blinding
Technique
|
|
Solid
Plate between
flanges(typical)
|
|
|
1/2"~12"
(DN15 ~DN300)
|
|
|
- 2~16 man-hours
- Gasket, bolts & nuts, tools
- Time for draining and line cooling
|
|
14"~24"
(DN350~DN600)
|
|
|
-
16~120 man-hours
- Gasket, bolts & nuts, tools
- Time for draining and line cooling
|
|
Size
|
Blinding(typical)
|
Deblinding(typical)
|
More
production
|
|
1/2"
~ 6"
|
1
to 4 hours
|
1
to 4 hours
|
2
to 8 hours
|
|
8"
~ 24"
|
4
to 12 hours
|
4
to 12 hours
|
8
to 24 hours
|
- time saving
for draining and line cooling is not included
- less pre-purge time
- immediate work after stopping line
Saving
cost for maintenance
- long life and simple design criteria
- no consumable parts except gaskets- it shall be replaced in case of
broken after visual checking
- no tools, wedges, crane, bolts are neccery
Positive
shutoff
- quick and positive response in emergency
- prevent vacuum losing
- prevent contamination by mixing
- prevent leaking accident in service
- prevent environmental pollution
|